SHED 1
Millet Destoner
NFIC-KUP-U09-01
Machine at a glance
Unit
Unit 9 — Millet Processing (Pre-existing)
Shed / location
SHED 1
Manufacturer
Suga Agro Tech
What this machine helps make
No validated product/technology mappings are currently available for this machine.
Operating SOP
1. Pre-operation checklist
• Empty stone trap completely
• Check blower outlet — not blocked
• Verify power connection
• Machine on floor mats — stable
• Check blower outlet — not blocked
• Verify power connection
• Machine on floor mats — stable
2. Start-up procedure
1. Switch on BLOWER first — wait 30 seconds
2. Load grain into hopper — max 80% capacity
2. Load grain into hopper — max 80% capacity
3. Operating steps / parameters
1. Switch on BLOWER first — wait 30 seconds
2. Load grain into hopper — max 80% capacity
3. Feed at rated 80 kg/hr — do not rush
4. Empty stone trap when 70% full
5. Hand-check output sample every 30 min for stones
6. Run blower empty 2 min after batch
2. Load grain into hopper — max 80% capacity
3. Feed at rated 80 kg/hr — do not rush
4. Empty stone trap when 70% full
5. Hand-check output sample every 30 min for stones
6. Run blower empty 2 min after batch
4. Shutdown procedure
6. Run blower empty 2 min after batch
5. Cleaning / sanitation
• Empty stone trap completely
• Brush hopper and outlet
• Log: grain type | weight in | weight out | stones removed | any observation
• Brush hopper and outlet
• Log: grain type | weight in | weight out | stones removed | any observation
6. Safety / PPE
• DUST MASK mandatory
• Never put hand into hopper while running
• Keep feet clear of stone trap outlet
• Never put hand into hopper while running
• Keep feet clear of stone trap outlet
7. Troubleshooting
Call supervisor if vibration increases, blower flow drops, or stones visible in output
8. Preventive maintenance
Routine prevention is embedded in the pre-operation and post-operation checks; no separate time-based preventive-maintenance interval is stated on the source card.